When to Install Doors During Finishing
Babeco · 2026

When should doors be installed during finishing?
Install doors at the very end of finishing: after the walls are finished and painted, after the parquet, after the bathroom thresholds, and when no other trade is working on site. Order Babeco doors once you can measure the openings; they are in stock and reach you within 2–3 days of order confirmation.
A typical order of work
- Plumbing, electrics and plastering.
- Tiles in bathrooms and kitchen, and the bathroom thresholds.
- Wall finishing and paint (or cladding).
- Flooring and parquet.
- Doors, then any cladding around them.
- Final cleaning and handover.
What goes wrong when doors go in early
- Before the parquet: the door rubs against the new floor once it is laid.
- Before the bathroom threshold: the door can rub, and a maintenance visit is needed.
- With other trades on site: knocks, paint and dust damage the new doors.
- On unfinished or out-of-plumb walls: gaps appear between the frame and the wall, and cladding cannot sit flush.
Getting the doors ready
- Measure openings and wall thickness once the walls are finished. See door opening sizes.
- Decide the swing direction of every door; it cannot be reversed after installation.
- Order with a few days' margin: our doors are in stock and reach you within 2–3 days of order confirmation.
- Keep the doors lying flat in a clean room until installation day, with all accessories on site.
After installation
Leave the doors closed for 24 hours so the fixing foam cures. Check each door before signing the handover record. The full process is in how WPC doors are installed, and the rules are in our installation terms.
Common questions
Do doors go in before or after the parquet?
After. Doors fitted before the parquet rub against it once it is laid, and the frame height no longer matches the finished floor. Measure door heights from the finished floor level, after tiles or parquet. The same rule applies to bathroom thresholds: fit the bathroom door after the threshold is in place.
When should I order the doors?
Once the walls are finished and you can measure the openings: width, height from the finished floor, and wall thickness. Our doors are in stock and reach you within 2–3 days of order confirmation, so there is no need to order months ahead. Order a frame extension in advance if any wall is thicker than 19 cm.
Can painters work while doors are installed?
No. No other trade may work on site during installation: paint, plaster dust and other work damage new doors and can stop the installer, and a return visit for an unready site is charged. Finish painting first, clear the site, then book the installation, and keep the doors closed for 24 hours afterwards.
Do doors go in before or after the painting?
After. Paint and plaster dust damage a new door, and the walls must be finished and plumb so the frame sits tight with no gaps. No other trade may work on site during installation. Book the installation once painting, parquet and bathroom thresholds are done, and leave doors closed for 24 hours afterwards.